Supplying Mozambique’s LNG projects: the 2026 guide for foreign companies
For a foreign supplier, entering Mozambique’s LNG projects means taking decisions before the first bid: who will contract and invoice, where the work will be performed, which team will be mobilised and which local content requirements apply. Those choices affect price, tax and the mobilisation timetable. This guide sets out the points to analyse before committing, and links to the detailed pages of the series.
The main projects, in one table
All of them sit in the Rovuma Basin off Cabo Delgado, in the far north of the country. Two are onshore plants on the Afungi peninsula near Palma; two are floating units moored offshore, grouped in one row below because Coral Norte replicates Coral Sul under the same operator. Dates and contractors are detailed, with sources, in Projects, timeline and contractors.
| Project | Operator and partners | Capacity | Status (October 2026) |
|---|---|---|---|
| Mozambique LNG (Area 1, onshore Afungi) | TotalEnergies 26.5%, Mitsui 20%, ENH 15%, ONGC Videsh, Bharat PetroResources, Oil India, PTTEP | 12.9 mtpa, two trains | Force majeure lifted November 2025; full restart announced 29 January 2026 with progress at 40% at that date; first LNG expected in 2029 |
| Coral Sul and Coral Norte FLNG (Area 4, offshore) | Eni operator through Mozambique Rovuma Venture (Eni, ExxonMobil, CNPC), with XRG (ADNOC), KOGAS and ENH | Coral Sul 3.4 mtpa producing since 2022; Coral Norte 3.6 mtpa | Coral Norte sanctioned in 2025; EPCIC awarded June 2026 to Technip Energies, JGC and Samsung Heavy Industries; first gas planned for the second half of 2028 |
| Rovuma LNG (Area 4, onshore Afungi) | ExxonMobil leads the onshore development for the Area 4 partners | 18.6 mtpa in 12 liquefaction modules | Force majeure lifted 20 November 2025; final investment decision targeted for 2026, not yet taken; August 2026: letter of intent to the SMDC joint venture (midstream) and about US$1.1 billion of pre-investment contracts for long-lead subsea equipment; September 2026: letter of intent to Saipem and Jan De Nul (upstream) and shorebase contracts in Pemba; start-up anticipated in 2031 |
Who needs a Mozambican presence, and when
There is no single threshold, but three situations usually settle the question.
- Work connected with Mozambique beyond a short mobilisation. Since 2026, the Corporate Income Tax Code (IRPC Code) has included permanent establishment tests for construction, installation and assembly sites lasting more than 90 days, and for services continuing within Mozambican territory for more than 90 days in aggregate in any twelve-month period. For services, the wording includes situations without physical presence and excludes digital services. Other cases under article 3 and any applicable double tax treaty must also be considered; invoicing from abroad or working remotely does not settle the question by itself.
- Your client’s contract or the procurement regime requires a local entity. Under the Local Content Law, goods and services in the exclusivity regime must be bought from Mozambican companies that meet its tests, the preference regime gives qualifying Mozambican and preferred persons a price advantage of up to 20% without excluding foreign bidders where local supply is unavailable, and the new Petroleum Law requires foreign service providers to associate with Mozambican persons.
- Your client requires local invoicing, or billing from abroad costs more than it saves. Concessionaires and EPC contractors commonly require suppliers with activity on site to invoice in meticais with Mozambican VAT, run payroll in the country and hold a local licence. Billing from abroad instead means a final withholding on the gross invoice: 20% under the general rule, or 10% for services connected with the concession contract under the petroleum regime, by law (Law 27/2014 as republished by Law 14/2017, art. 28 no. 2) or under the Area 1 and Area 4 concession contracts (art. 11.4(e)), whose conditions are set out in the tax guide. Which rate applies depends on the taxpayer, the services and the contract, not on a supplier’s position in the chain.
Pure equipment exports to Mozambique, delivered and invoiced from abroad with no local activity, generally do not require an entity. Once people, equipment or a site office are in the country for a sustained period, the analysis changes. A single contract that bundles equipment with installation, commissioning or supervision in Mozambique has to be analysed as a whole: the on-site services can create a permanent establishment, and the tax authority may then seek to attribute to it income from the whole contract, including part of the supply price. Where supply and services are split into separate contracts, the split must be genuine and priced at arm’s length.
Choosing the vehicle: subsidiary, branch or partnership
| Option | Typical use | Aspects to consider |
|---|---|---|
| Sociedade por quotas (Lda) | Suppliers with a small, stable group of shareholders | Separate legal person with capital in quotas (ownership interests); may be incorporated with a sole shareholder (Commercial Code, art. 257); a Mozambican legal person under the Local Content Law when its seat and management are in Mozambique; general 32% corporate tax |
| Sociedade anónima (SA) | Where capital organised in shares and board-based governance suit the group or future partners | Separate legal person with capital in shares; may also be incorporated with a sole shareholder; same tax treatment as an Lda; a simplified form (SAS) also exists in the Commercial Code |
| Branch of a foreign company (sucursal) | Single large contract, parent wants direct control | Parent liable for branch obligations; taxed as a permanent establishment; not a Mozambican legal person for local content purposes |
| Representative office | Market study and preparatory acts only | May not carry on the commercial activity itself: no invoicing or execution of the supply; rarely useful once a tender is won |
National participation is a question of capital composition, not of legal form: an Lda or an SA can both have Mozambican shareholders, and status under the Local Content Law (Mozambican legal person, preferred person) follows the legal requirements and the substance of the arrangement, not the company type. Where a partnership is chosen, governance, profit split and exit must be agreed up front.
In our experience, set-up of an Lda or SA takes four to eight weeks once the parent’s documents are duly legalised and translated into Portuguese, according to the country of origin and the requirements of the registry (Mozambique is not a party to the Apostille Convention, so consular legalisation is usually needed): name reservation, articles of association, commercial registration with the beneficial ownership information required by the Commercial Code (art. 99), publication, tax number (NUIT), the activity licence, social security registration and bank account. Commercial registration, the activity licence, foreign-trade operator registration where applicable, local content certification and the client’s prequalification are separate steps; none replaces another. The timing depends on document readiness, the licence required for the activity and the bank’s own checks. Foreign capital should be registered under the exchange legislation at entry, because that registration is what later supports the transfer of dividends and capital; the investment regulation sets a minimum foreign direct investment of MZN 6.5 million in equity contributions from the investor for that guarantee (Decree 8/2024, art. 4).
Local content: what Law 9/2026 changes
Law 9/2026 of 3 June 2026 is the first dedicated Local Content Law for petroleum operations, approved alongside the new Petroleum Law (Law 8/2026). It applies to concessionaires, their contractors and every entity that contracts with them, and it ranks bids by local content before price. The points that matter most for a foreign supplier:
- Who you are: a Mozambican legal person is one registered in Mozambique with its seat and effective management there; a preferred person is a national legal person with at least 20% Mozambican capital and a predominantly Mozambican workforce and payroll. There is no 51% rule.
- How you are ranked: three procurement regimes (preference, exclusivity and free market). Under preference, a qualifying Mozambican supplier wins with a price up to 20% above the lowest comparable foreign bid. Exclusivity applies to goods and services with at least 80% national production factors, 20% Mozambican capital and 50% Mozambican payroll.
- How it is enforced: a Local Content Authority approves procurement plans, accredits certifiers, publishes the list of certified suppliers, inspects and fines (USD 50,000 to USD 300,000; 1% to 10% of the contract for false information). The Council of Ministers approved the regulation and the Authority’s statute on 13 October 2026; as of 18 October the published text, decree number and entry into force had not been confirmed.
The definitions, the three regimes, the structures that fit each and the penalties are explained in the Local Content Law guide.
Tax: the headline rates for suppliers
| Item | Rate or rule | Comment |
|---|---|---|
| Corporate income tax (IRPC) | 32% | Concessionaires are ring-fenced per concession under the petroleum regime; subcontractors fall under the general regime |
| Value added tax (IVA) | 16% | Exemptions for approved projects cover listed goods and named importers only |
| Final withholding on non-residents without a permanent establishment | 20% of gross; 10% for telecommunications and international transport services, including the assembly and installation of equipment connected to those services (art. 62, no. 4 a)) | The most common surprise for suppliers billing from abroad; treaties may reduce it if the certified form is in place by the taxable event, which since 2026 can be the recognition of the cost, before any transfer |
| Withholding on dividends | 20% (10% for shares listed on the Mozambique Stock Exchange, BVM) | Reduced under treaties in force with South Africa, Portugal, UAE, India, Italy, Mauritius, Vietnam and Macau |
| Capital gains | Autonomous 32% rate since 1 January 2026 | Relevant when a stake in a Mozambican vehicle is sold |
| Permanent establishment | More than 90 days in any twelve months for sites, and for services continuing within Mozambican territory (a wording that includes situations without physical presence) | New domestic threshold from 2026; other cases in art. 3 apply regardless of duration; treaties may provide longer thresholds |
| Petroleum regime withholding | 10% final on services connected with the concession contract supplied by non-residents (Law 27/2014, republished by Law 14/2017, art. 28 no. 2) | Legal basis (art. 28 no. 2) or, for Area 1 and Area 4, contractual basis (EPCC art. 11.4(e)); each has its own conditions on the taxpayer, the services and the beneficiary. Independent EPC and lower-tier contracts need a separate assessment, otherwise the general 20% applies |
Four topics recur in tax audits: transfer pricing documentation for intra-group charges, VAT on imported equipment outside the project’s exemption list, VAT self-assessed on services acquired from non-residents (reverse charge), and withholding on offshore invoices settled late, which the tax authority then assesses on the Mozambican payer. The tax guide for subcontractors covers the rules, the 2026 changes and the compliance calendar.
People: quotas, hiring regimes and payroll
Foreign staff are limited to a share of headcount. The Labour Law sets 15% for micro employers (up to 10 workers), 10% for small (11 to 30), 8% for medium (31 to 100) and 5% for large employers; the petroleum and mining regulation (Decree 63/2011) uses 10% up to 10 workers, 8% from 11 to 100 and 5% above 100. Within the quota, hiring requires notification to the labour authority; outside it, a work authorisation is required. Short-term work is possible for up to 120 days a year under the general regulation (Decree 88/2024) and up to 180 days in petroleum and mining. The Area 1 and Area 4 projects have a regime of their own under Decree-Law 2/2014: the aggregate quota of foreign staff for each project, including contractors and subcontractors, is fixed in the workforce plan approved with the development plan; hires within it are made by prior notification and a further notification within 15 days of entry, short-term work runs up to 180 days a year, and hires beyond the plan need a work authorisation (arts. 18 and 20). Immigration (visa and residence) and tax residence are separate frameworks with their own rules.
Employees on the Mozambican payroll are subject to monthly personal income tax (IRPS) withholding and to social security (INSS) contributions of 4% from the employer and 3% from the employee. Foreign workers covered by another country’s social security system are not required to register with INSS, but the exemption requires proof of that coverage to be provided to INSS: a certificate authenticated by the Mozambican consulate in the country of origin, or whose conformity with the issuing country’s formalities is declared by the competent authority (Decree 51/2017, art. 4). A foreign beneficiary who permanently leaves Mozambique before becoming entitled to a pension may request a refund of the contributions paid in their name to the pension branch, provided INSS has not concluded a bilateral social security agreement with their country of origin; the request must be made within one year of the payment date of the last contribution (art. 123 nos. 3 and 4). The regimes, timings and the 2026 residence rules are in Work permits and payroll.
Transferring profits and capital abroad
Mozambique operates exchange controls under the Exchange Law (Law 28/2022) and the Bank of Mozambique’s Notice 3/GBM/2024. The documents depend on the nature of the transfer: dividends and other investment income, interest, repayment of loan principal and payments for imported services each have their own rules (arts. 37 and 51 to 56). For dividends of foreign direct investment the bank checks the exchange registration of the investment, the shareholders’ resolution approving the distribution, proof that the tax obligations relating to the transaction have been met and, where applicable, an independent auditor’s declaration on the profits (art. 52). Payments for services billed from abroad do not depend on a registered equity investment, but do require evidence of compliance with the relevant tax obligations. Treaty relief on withholding must be requested on the official form by the time the taxable event occurs (Ministerial Diploma 113/2006, art. 2), and since 2026 that event can be the recognition of the cost, before the bank transfer; otherwise tax is withheld in full and can be reclaimed within two years counted from the taxable event (art. 3). Plan the transfer route when you set up, not when the first dividend is declared.
A realistic sequence for a new supplier
- Weeks 1 to 2: decide the vehicle and the partner structure against the Local Content Law definitions; collect and legalise parent documents; reserve the name.
- Weeks 3 to 8: incorporate and file the beneficial ownership information, register for tax and social security, open the bank account, register the foreign investment, obtain the activity licence. Timing depends on documents, licence type and bank checks.
- From week 6: register on the operators’ and EPC contractors’ vendor portals; start local content certification once the Authority’s procedure is available; file work authorisations for the first expatriates, which take longest.
- From the start of activity and hiring: run payroll, file the applicable returns and payments, and keep transfer pricing and local content records from the first transaction.
Frequently asked questions
Do I need a Mozambican company to bid for LNG work?
Not always to bid, but increasingly to win and to perform. Under the Local Content Law, exclusivity goods and services must be bought from qualifying Mozambican companies and the preference regime gives Mozambican and preferred persons a price advantage, the Petroleum Law requires foreign service providers to associate with Mozambican persons, and performing certain works or services in Mozambique for more than 90 days may constitute a permanent establishment under domestic law, with the applicable double tax treaty also to be analysed.
How long does it take to set up a company in Mozambique?
Four to eight weeks for a limited company once the parent company’s documents are legalised and translated into Portuguese, with bank account opening and foreign investment registration running in parallel. Licensing for regulated activities can add time.
What is the withholding tax on services billed from abroad?
Twenty percent of the gross amount as a final tax on non-residents, with 10% for telecommunications and international transport services, including the assembly and installation of equipment connected to those services. Under the petroleum regime, by law (Law 27/2014, art. 28 no. 2) or under the Area 1 and Area 4 concession contracts (art. 11.4(e)), services connected with a concession contract supplied by non-resident subcontractors carry a 10% final withholding when the respective conditions are met; the rate follows those conditions, not the supplier’s position in the chain (see the tax table above). Treaties can reduce it if the certified form is in place by the taxable event, which since 2026 can be the recognition of the cost rather than the payment. Invoicing through a local entity changes the position to the resident regime; it is not an exemption.
Does the Local Content Law apply to my client’s subcontractors?
Yes. Law 9/2026 applies to every entity that contracts with concessionaires or their contractors, and those entities must impose local content obligations on their subcontractors by contract, with joint liability.
Can foreign staff work on a short-term basis without a full work authorisation?
Yes. The general regulation allows short-term work of up to 120 days per calendar year, and the petroleum and mining regulation up to 180 days per year, by notification from the host entity. Longer assignments need a quota communication or an authorisation.
Sources
- Lei n.º 9/2026, de 3 de Junho (Lei de Conteúdo Local), via INP
- Lei n.º 8/2026 (Lei dos Petróleos), Boletim da República I Série n.º 104, 2.º suplemento, via INP
- Conselho de Ministros: comunicado da 29.ª sessão ordinária, 13 Outubro 2026 (aprovação do Regulamento da Lei de Conteúdo Local)
- Lei n.º 13/2023 (Lei do Trabalho), via Tribunal Supremo
- Decreto n.º 88/2024 (contratação de cidadãos estrangeiros), via Ministério do Trabalho
- Decreto n.º 63/2011, de 7 de Dezembro (contratação de cidadãos estrangeiros no sector de petróleos e minas), Boletim da República I Série
- Area 1 concession contract (EPCC, 2006), Government, Anadarko Moçambique Área 1 and ENH, via INP
- Area 4 concession contract (EPCC, 2006), Government, Eni East Africa and ENH, via INP
- Decreto-Lei n.º 2/2014 (regime especial das Áreas 1 e 4 da Bacia do Rovuma), via ARENE
- Lei n.º 27/2014 republicada pela Lei n.º 14/2017 (regime fiscal das operações petrolíferas), via INP
- Regulamento da Segurança Social Obrigatória (Decreto n.º 51/2017, republicado pelo Decreto n.º 56/2024), via INSS
- Código Comercial, Decreto-Lei n.º 1/2022, de 25 de Maio, Boletim da República I Série n.º 99, 3.º suplemento
- Leis n.º 10/2025, 11/2025 e 12/2025, de 29 de Dezembro (alterações ao IVA, IRPS e IRPC), Boletim da República I Série n.º 248
- Lei n.º 8/2023, de 9 de Junho (Lei do Investimento Privado), Boletim da República I Série n.º 111
- Decreto n.º 8/2024, de 7 de Março (Regulamento da Lei do Investimento Privado), Boletim da República I Série n.º 48
- Banco de Moçambique: Aviso n.º 3/GBM/2024, normas e procedimentos para a realização de operações cambiais
- HCCH: status table of the Apostille Convention
- TotalEnergies: full restart of Mozambique LNG (29 January 2026)
- JGC: EPCIC contract for Coral Norte FLNG (8 June 2026)
- ExxonMobil in Mozambique: letter of intent to the SMDC joint venture for Rovuma LNG (10 August 2026)
- ExxonMobil in Mozambique: over US$1 billion in pre-investment contracts for Rovuma LNG (17 August 2026)
- ExxonMobil in Mozambique: upstream EPCI selection and shorebase service providers (10 September 2026)
General information prepared by dBA from legislation and public sources available at the date shown. It is not tax or legal advice. Confirm how it applies to your case with our team before acting.
Related services
Setting up to supply Mozambique’s gas projects?
Tell us the contract, the timeline and where your people will sit. We come back within 24 business hours with a first assessment of the structure, the costs and the sequence.